Effects of Contract Management on Project Performance at the Road Development Agency

Authors

  • Mwenya Mwenya University of Zambia image/svg+xml Author
  • Dr. Richard Mwale Kasongo THE UNIVERSITY OF ZAMBIA , University of Zambia image/svg+xml Author

DOI:

https://doi.org/10.59413/ajocs/v7.i3.28

Keywords:

Project performance, Contract Management, Cost, Time, Quality

Abstract

The study sought to establish the effects of contract management on project performance at the Road Development Agency in Zambia. It was anchored in institutional theory and the iron triangle theory. Contract management in procurement involves overseeing contracts with suppliers and buyers to ensure adherence to obligations outlined in the Public Procurement Act No. 8 of 2020 as amended by the Public Procurement (Amendment) Act No. 17 of 2023 and Statutory Instrument No. 30 of 2022 (Public Procurement Regulations, 2022) as well as the terms and conditions outlined in the contract. Contract management is vital for managing costs, ensuring quality, meeting deadlines, and resolving disputes. Zambia, like many African countries, faces challenges with incomplete construction projects, affecting economic growth linked to the sector. Although research exists on project performance in Zambia, there is a lack of understanding on how contract management affects project performance in Zambia's public sector. This study aimed to establish the effects of contract management on project performance at the Road Development Agency in Zambia. The study used a cross-sectional study design and quantitative data from structured questionnaires (n = 31). Descriptive statistics and multivariable linear regression were used for quantitative analysis. Compliance with contractual obligations (93.6%) emerged as the most prominent performance objective, followed by timelines, quality standards, and cost (each 83.9%). Contract management practices were widely adopted (mean = 4.52, SD = 0.89), with compliance, transparency, and professionalism highly reported. Quality performance scored highest (mean = 3.67, SD = 0.64), followed by cost (mean = 3.00, SD = 0.71), while time performance was lowest (mean = 2.63, SD = 0.67), indicating challenges with delays. Regression analysis showed no statistically significant association between contract management practices and project performance (p > 0.05). While contract management is well established at the Road Development Agency, its impact on project performance is limited by challenges in time and cost control. Strengthening monitoring systems, enhancing managerial capacity, and promoting integrated management approaches are essential to improve project outcomes.

Downloads

Download data is not yet available.

References

Ahmed, R., 2023. Project performance measures and metrics framework. In Research Handbook on Project Performance (pp. 11-22). Edward Elgar Publishing.

Ali, N., & Wali, K. (2019). Evaluation of Construction Delay of Public Projects in Erbil Governorate. Cihan University-Erbil Scientific Journal. https://doi.org/10.24086/CUESJ.V3N1Y2019.PP18-26.

Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, it’s time to accept other success criteria. International Journal of Project Management, 17(6), 337–342. https://doi.org/10.1016/S0263-7863(98)00069-6.

Basheka, B.C. (2014) ‘Procurement planning and accountability of local government procurement systems in developing countries: Evidence from Uganda’, Journal of Public Procurement, 14(2), pp. 173–200.

Changalima, I.A., Mchopa, A.D., & Ismail, I.J. (2023). "Supplier monitoring and procurement performance in the public sector in Tanzania: the moderating role of contract management difficulty." IIM Ranchi Journal of Management Studies, Vol. 2 No. 1, pp. 16-30. https://doi.org/10.1108/IRJMS-04-2022-0039.

Coleman, E., Nooni, I., Fianko, S., Dadzie, L., Neequaye, E., Owusu-Agyemang, J., … & Ansa-Asare, E. (2020). Assessing contract management as a strategic tool for achieving quality of work in the Ghanaian construction industry. Journal of Financial Management of Property and Construction, 25(1), 41-60. https://doi.org/10.1108/jfmpc-08-2018-0046.

Dawande, M., Janakiraman, G., Qi, A., & Wu, Q. (2019). Optimal incentive contracts in project management. Production and Operations Management, 28(6), 1431-1445. https://doi.org/10.1111/poms.12997.

Du Plessis, H., & Oosthuizen, P. (2018). Construction project management through building contracts: A South African perspective. Acta Structilia, 25(1), 152–181.

Eaton, C., Patel, S., Glandon, K.L., Weger, K., Mesmer, B. and Moreland, R., 2022. Legacy of faster, better, cheaper? Cost, schedule, and performance objectives: Understanding the impact of NASA policy on perceptions of failures. Space Policy, 62, p.101515.

Government of the Republic of Zambia (2022) Eighth National Development Plan (8NDP) 2022–2026: Socio-economic transformation for improved livelihoods. Lusaka: Ministry of Finance and National Planning.

Forbes, B., & Brady, M. (2019). Ex-post service contract performance management. International Journal of Business Performance Management, 20(2), 130. https://doi.org/10.1504/IJBPM.2019.10018775

Gomes, C., Small, M., & Yasin, M. (2019). Towards excellence in managing the public-sector project cycle: a TQM context. International Journal of Public Sector Management, 32(2), 207-228. https://doi.org/10.1108/ijpsm-11-2017-0315.

Government of Zambia. (2022). Statutory Instrument No. 30 of 2022: The Public Procurement Act, 2020 (Act No. 8 of 2020) The Public Procurement Regulations. Government of Zambia.

Iimi, A. (2020). Performance-Based Road Contracts in Zambia. Review of Industrial Organization, 57, 107–129. https://doi.org/10.1007/s11151-019-09714-5.

International Journal of Recent Research in Commerce Economics and Management (IJRRCEM) (2021) International Journal of Recent Research in Commerce Economics and Management.

Kafula, B., Mwanza, B. and Mwanaumo, E., 2023. Contract Management as a Tool for Successful Project Performance: A Pragmatic Study on Construction Projects in Zambia.

Kapsali, M., Roehrich, J., & Akhtar, P. (2019). Effective contracting for high operational performance in projects. International Journal of Operations & Production Management, 39(2), 294-325. https://doi.org/10.1108/IJOPM-10-2017-0604

Kineber, A., Othman, I., Oke, A., Chileshe, N., & Alsolami, B. (2020). Critical Value Management Activities in Building Projects: A Case of Egypt. Buildings. https://doi.org/10.3390/buildings10120239

Lee, C., Chong, H., Li, Q., & Wang, X. (2020). Joint contract–function effects on BIM-enabled EPC project performance. Journal of Construction Engineering and Management, 146(3). https://doi.org/10.1061/(ASCE)CO.1943-7862.0001766

Lu, P., Cheng, X., Wei, Z., Song, Y., & Wu, J. (2019). Quality management practices and inter-organizational project performance: moderating effect of governance mechanisms. International Journal of Project Management, 37(6), 855-869. https://doi.org/10.1016/j.ijproman.2019.05.005

Mahajan, A., & Baride, M. (2023). Planning and contract management strategies for successful EPC project execution. Day 2 Tue, October 03, 2023. https://doi.org/10.2118/216194-MS

Manzanares, F. V., García-Segura, T., & Pellicer, E. (2023). Contract conditions and BIM use effectiveness to improve project performance. Advances in Civil Engineering, 2023, 1-11. https://doi.org/10.1155/2023/2629608

Mudzvokorwa, T., Mwiya, B., & Mwanaumo, E. M. (2019). Improving the Contractor-Subcontractor Relationship Through Partnering on Construction Projects in Zambia. KICEM Journal of Construction Engineering and Project Management.

Nsefu, M. K., Mwanaumo, E. M., Mambwe, M., Daka, J., & Mwanza, B. G. (2020). Effectiveness in the Contract Management Performance within the Lusaka Provincial Administration – A Balanced Scorecard Application. Proceedings of the 2nd African International Conference on Industrial Engineering and Operations Management.

Oyieyo, P., Rambo, C., & Ndiritu, A. (2020). Construction Time Overrun Related Risks as a Determinant of Completion of Public Private Partnership Projects in Kenya. Case Study of Sondu Miriu Hydropower Project. European Journal of Business and Management, 5. https://doi.org/10.24018/ejbmr.2020.5.5.493.

Shang, K.; Wu, J.; Cao, Y. (2023). Study on the Impact of Trust and Contract Governance on Project Management Performance in the Whole Process Consulting Project—Based on the SEM and fsQCA Methods. Buildings, 13, 3006. https://doi.org/10.3390/buildings13123006

Small, E., Bakry, I., & Ayyash, L. (2019). Evaluating the effect of TQM on MEP construction productivity and project delivery in Dubai. International Journal of Construction Management, 21, 1061-1075. https://doi.org/10.1080/15623599.2019.1602584.

Scott, W. R. (2005). Institutions and organizations: Ideas and interests (3rd ed.). Sage Publications.Troya-Martinez, M., and Wren-Lewis, L. (2022). Managing relational contracts. Journal of the European Economic Association. https://doi.org/10.1093/jeea/jvac049.

Uwiringiyimana, T., & Dushimimana, J. de D. (2024). Effect of Procurement Contract Management Practices on Performance of Public Institutions. A Case of Integrated Polytechnic Regional College (IPRC) Musanze, Rwanda. African Journal of Empirical Research, 5(1), 476–487. https://doi.org/10.51867/ajernet.5.1.47.

Vokurka, R.J. (2008) ‘Supplier partnerships: A case study’, Production and Inventory Management Journal, 49(2), pp. 30–38.

Watt, A. (2018) Project management. Victoria, BC: BCcampus.

Zambia Public Procurement Authority. (2020). Public Procurement Act No. 8 of 2020. Government of the Republic of Zambia.